Friday, 17 June 2011

17.6.2011 - Carpenter

The carpenter arrived to finish off architraves etc. Should be finished by Tuesday 21.6.11. Still no tiler!

16.6.2011 - Tiler

Tiler finally arrived but the truck that was supplying the motor and sand broke down. So they said they would come back tomorrow.  Our water tank arrived. SS said the painter is due to come on 23/6. Carpenter should be there tomorrow.

15.6.2011 - Plumber installed rest of downpipes - no tiler

14.6.2011 - tiler supposed to start - didn't turn up

9.6.2011 - Kitchen, landry & vanity installed


8.6.2011 - Waterproof & kitchen

The waterproofing has been completed and did a great job. The kitchen, laundry etc  arrived today. The carpenter came and  put on the front door and finished off the eaves around the garage. He put up a few frames ready for the tiler.

7.6.2011 - Waterproof

The waterproof getting done today.  They will need another day to complete. The front door and garage internal door semi put in t lock up.