Thursday, 21 July 2011
27.6.11 - Carpenter
The carpenter was there until about 12. He finished the rest of the architraves upstairs. No tiler. Here we go again.
24.6.11 - update for the week
We spoke to SS today. Wisdom advised that they do not have the same toilet now and we had a choice of toilets that were similar. He advised the main floor should start next week. The carpenter will be there on Monday. The sander should be there Wednesday and the painter can come in on Thursday/Friday.
23.6.11 - Tilers
The tilers turned up about 1pm and did alittle more in the bathrooms. More architraving turned and doors for downstairs arrived.
22.6.11 - Bench tops
Our bench tops went in and we were so excited. It is starting to look like a kitchen. It is all covered up so it doesn't get dirty and paint on it. No one else there today.
21.6.11 - Electrician & tiler
The electrician put in all the power points and lights. They also put in our rangehood and was exciting to put the lights on. The tiler did alittle more tiling. Slow but doing a good job.
20.6.11 - Tiler & carpenter
The tiler turned up again. He continued on with bathroom tiles. The carpenter was also there putting in all the architraves.
18.6.11 - Tiler
The tiler finally came today. They did all the white tiles in the showers only. Lets hope he will turn up tomorrow!